Register


3 months Free Trail

Get world class research developed by an in house team of professionals backed with strong institutional support. With reports that span across time horizons, styles and easily actionable strategies, you are never too far from executing a winning trade.

Key features and benefits of Registeration :
  • My Portfolio : Access 360° View not only of your Portfolio with Emkay, but all your Investment Portfolios
  • Emkay Research : Get Emkay's exclusive Research Reports & Trading Ideas.
  • My Watch list : Track your favorite stocks, Derivatives, Currencies, Commodities, Mutual funds on the go
  • Markets : Grab Stock Market Information at your fingertips
  • News & Announcements : Stay Updated 24x7 with news that matters.
  • Alerts : Get Alerts on Emkay Research, Trading Ideas, news on your portfolio holdings & watchlist

Forgot password

Change password

Forgot Customer Code

Would you like to create a personalised login id for logging in to Emkay Website ?

Change Personalised Login ID

Total cost overrun in 84 MMI projects is more than Rs 1.2 lakh crore: CAG report

Share Source By

Dion Global

09 Jan 2019

The Comptroller and Auditor General (CAG) has said that the total cost overrun of 84 Major and Medium Irrigation (MMI) projects under the Accelerated Irrigation Benefit Programme (AIBP) was Rs 1,20,772.05 crore, which was 295 per cent of their original cost.

The report tabled before the Lok Sabha on Tuesday said the implementation of projects under the Accelerated Irrigation Benefit Programme (AIBP) was "tardy" and monitoring by central and state agencies was "lax".

The delays were attributed to shortfall in land acquisition, inability to obtain statutory clearances in advance, changes in design and scope of work.

The report noted that the delays in the implementation of projects, together with inefficient works management, led to the cost overrun.

"The total cost overrun in 84 MMI projects, including 16 completed and 68 ongoing projects, was 1,20,772.05 crore which was 295 per cent of their original cost," it said.

The realisation of envisaged benefits in terms of Irrigation Potential (IP) creation was only 68 per cent in MMI projects and 39 per cent in Minor Irrigation schemes.

"The utilisation of IP created was 65 per cent and 72 per cent respectively for MMI projects and MI schemes. There were deficiencies in works management such as delays in award of work, splitting of works, incorrect phasing of project implementation, execution of sub-standard work, undue benefits to contractors," it said.

The extra financial implications seen in audit were to the extent of Rs 1,337.81 crore towards irregular/wasteful/avoidable/extra expenditure and Rs 303.36 crore due to "undue favour" to the contractor, the report observed.